Week 1 progress

On Day 1 the surveyor marked out where the piers needed to go. 

On Day 2 the marram glass was removed from the building area and a bit of the top soil was removed in parts to give a more level building space. 

 

A machine was then brought in to dig deep holes for the piers. Cardboard tubes were then placed in the hole so that the sand didn’t cave in. The cardboard tubes used on our build were Formatubes.

  Day 4, the holes were filled with concrete and had a metal footing put in the top. 