By mid of Week 6 all the window frames installed and most of the house wrapped with Enviroseal wrap. Spotted Gum decking also delivered ready for the deck and porch.

Wrapping still needed on the beach side. However, the living room window frame has been installed. An extra steel beam was also installed under the living room window sill.

Framing added for the fireplace.

IMG_8639

Newly installed living room window.

Along with newly installed dining room French doors and windows on either side.

Kitchen window frames installed but unfortunately the wrapping was over the windows. Can’t wait to see the windows without the wrapping.

View from Bedroom 2.

By the end of Week 6, glass had been installed in all the windows. Here are the living room windows …

… dining room double doors and windows …

… and kitchen windows – still all wrapped up! 

Only now noticed that there is a bit of a water view from Bedroom 4 – this was a bonus as we never thought there would be a view from Bedroom 4.

IMG_8663

Work progressed on the deck. Around half of the spotted gum installed along with the posts.

On the deck we will have a BBQ just under the window. Loving the view of the water through the house from the BBQ spot.

View from the dunes at the end of Week 6.

View of the front at the end of Week 6. 