Week 8 progress

If this was Grand Designs, the sad music would start to play now 🙁

The roof has been delayed for another week as the roofers are still struggling to get the fascia, gutters and roof sheets from the mainland. It is not clear if this is due to disruption from the summer bushfires, Toll’s cyber attack, the wharf strike at Port of Melbourne or disruption due to the COVID-19 pandemic.  All we know is still no roof this week!

Everything looked the same from the outside …

… but it looked like a bit more work happened on the plumbing on the inside. Below you are see the vanity waste with a vent pipe.

IMG_8740

Looking forward to enjoying this view, minus the scaffolding, while washing the dishes.